Some British-era bridges in better condition than those built after independence: Parliament panel

The committee came down hard on the national transporter and said that the delay in sanctioning bridgework was putting the lives of passengers at risk.

Published: 09th February 2018 09:09 PM  |   Last Updated: 09th February 2018 09:09 PM   |  A+A-

Parliament. (Express Photo | Shekhar Yadav)

By PTI

NEW DELHI: Some British-era railway bridges were in a better condition than the ones built after independence, a parliamentary committee report said today, blaming the nexus between officials and contractors for the poor quality of bridges.

The Public Accounts Committee which presented its report -- Maintenance of Bridges in Indian Railway -- in Parliament, came down hard on the national transporter and said that the delay in sanctioning bridgework was putting the lives of passengers at risk.

"The committee note that while certain railway bridges constructed during British rule are in good condition, railway bridges constructed or reconstructed after independence are of inferior quality and need frequent repair.

"Nexus between railway officials and few contractors severely affect the quality and life of its construction," the report stated.

The committee headed by Congress's Mallikarjuna Kharge recommended that the tender for construction or rehabilitation of bridges be done through e-tendering so as to make the system transparent and to attract large number of reputed and competent construction companies in the tendering process.

It also said that companies or contractors who fail to ensure quality and long life of bridges be debarred from participating in future tenders and penalised for it.

The committee which based its report on a 2015 CAG report on railway bridges and representations by Railway Board members, expressed its shock that out of the 3,979 bridgesworks sanctioned by the Railway Board, work on 710 bridges remains to be completed as on March 2015.

According to a Railway Board letter in October 2017, the Central Railways has 61 bridges that need repair, East Central Railways has 63, South Central Railways has 41 and Western Railways has 42 bridges pending rebuilding.

The committee noted that while the paucity of funds was cited as a reason for shortfall in achievement of targets for bridgeworks, the budget grant provided was not utilised to the tune of Rs 60.95 crore per annum.

"The committee has desired that a strategic management system be developed for fast tracking sanction of rehabilitation or reconstruction of bridges within a time frame based on priority for safety", the report stated.

 

Stay up to date on all the latest Nation news with The New Indian Express App. Download now

Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.

IPL2018