PM Modi inaugurates Chennai Metro Phase II stretch, takes rail ride with CM Vijay

Tamil Nadu BJP accorded him a warm welcome by also holding cultural programmes like traditional dance shows on specially earmarked spaces on the roadside near the airport.
Chief Minister C Joseph Vijay (L) receives PM Modi at Chennai airport.
Chief Minister C Joseph Vijay (L) receives PM Modi at Chennai airport.(Photo | ANI)
Updated on: 
2 min read

CHENNAI: Prime Minister Narendra Modi and Chief Minister Joseph Vijay flagged off the 15 km Yellow Line, the first stretch of Corridor 4 in Chennai’s Phase 2 metro expansion. The Rs 4,900 crore stretch is a complex piece of urban infrastructure, built around a 3.5 km double-decker viaduct that cuts through one of the city’s most congested corridors and now links the Western corridor boosting ridership.

Both Modi and Vijay took the Metro from Porur Metro station and Poonamallee Bypass as officials briefed the Prime Minister about the project in the presence of the Chief Minister. This is also the first time platform screen doors (PSD) are installed in an elevated stretch.

The train service ran from 4 pm to 9 pm on the inaugural day. From Monday, services will operate from 7 am to 9 pm, with work yet to be completed on the remaining six stations and at the entry and exit points of Vadapalani station.

As of now, commuters will reach Vadapalani station by a link bridge connecting Phase 1 and Phase 2. That arrangement will hold until the new entry and exit at Vadapalani, and the six other stations between Vadapalani and Porur, are ready by December.

“Everything will be completed after civil work ends in December,” T Archunan, director of projects at Chennai Metro Rail Limited (CMRL), said. Civil work on the six stations will finish that month, but the line is not done at that point. The stations still need statutory approvals and fire licences, and a second inspection by the Commissioner of Railway Safety (CRS), without which, CMRL cannot commit to opening them.

With Phase I having a ridership of one crore in the last three consecutive months, officials expect it to rise, the reason being it takes more than an hour to reach Vadapalani from Poonamallee Bypass, which is dotted by institutions, residential areas and business hubs.

Chief Minister C Joseph Vijay (L) receives PM Modi at Chennai airport.
PM Modi to launch projects worth over Rs 13,000 crore during Chennai visit on Sunday

Trains on the stretch will initially be operated manually, despite being driverless. Archunan said CMRL will first operate with drivers for two to three months, collecting reports and performance data. Only if the trains run consistently over that period will the system be switched to driverless operation.

This will result in Chennai Metro's operational network reaching 69 km and result in the city taking fifth place, along with Hyderabad Metro, which also has 69 km of metro lines put into operation. Currently, the city is placed seventh, way below Delhi, Mumbai, Bengaluru, Kolkata, Hyderabad and Ahmedabad.

With the opening of this stretch, the focus now rests on the wider Koyambedu–Alandur stretch, nearly 29.6 km in all. The corridor was first planned only as far as Chennai Trade Centre (CTC) (26km stretch). Officials now expect to complete the 3.6 km link from CTC to Alandur, which runs through the congested Butt Road stretch.

Trial runs from Koyambedu to CTC are expected by the end of November. All track work up to CTC is complete. Extending trials to Alandur will take about two more months, because track there has yet to be laid.

Meanwhile, CMRL has floated a tender for last-mile connectivity at 41 Phase 1 stations and is about to award it. No equivalent tender has been issued yet for Phase 2.