BRO completes re-alignment work on Kishtwar-Himachal Pradesh road

The road passes through the rough mountain terrain with over hanging and half tunnelling stretches, mostly in hard rock strata.

Published: 14th June 2020 08:39 PM  |   Last Updated: 14th June 2020 08:39 PM   |  A+A-

Border Roads Organisation

For representational purposes

By PTI

JAMMU: The re-alignment work of Galhar-Sansari road, connecting Kishtwar district of Jammu and Kashmir with Himachal Pradesh, has been completed by the Project Beacon of the Border Roads Organisation (BRO), an official spokesperson said on Sunday.

The new bypass road has been built by 118 Road Construction Company of the General Reserve Engineering Force (GREF) to ensure round-the-year movement of all types of vehicles, besides providing connectivity to various villages in the remote Paddar area of Kishtwar, the spokesperson said.

He said the new road would help in evading the earlier world's dangerous rock cut stretch on which only light vehicles used to ply.

Complimenting the GREF, District Development Commissioner, Kishtwar, Rajinder Singh Tara said the work on the re-alignment has ensured employment of locals along with development of the hilly district.

"It will also increase the tourism potential of the Padder sub-division and Pangi valley of Himachal Pradesh thus boosting socio-economic development of the entire region," he said.

The road passes through the rough mountain terrain with over hanging and half tunnelling stretches, mostly in hard rock strata.

The sector also experiences heavy snowfall, flash floods and sub-zero temperature during winters making tough working conditions for GREF employees and the administration.

The road witnesses heavy traffic during Mindal Mata, Chittoo Mata and Machail Mata Yatra and is also the alternative route which connects Jammu and Kashmir to Himachal Pradesh during winters as the Rohtang Pass, Sach Pass remains closed, the spokesperson said.

Keeping in view of these issues, he said a re-alignment for this stretch was proposed and construction of Galhar-Sansari road from 55.100 to 58.775 km with net length of 10.925 km commenced in August 2018 and was completed in record time.

He said the proposed date of completion for formation work for 10 m width on this stretch has been fixed for June 2021 and the black topping to be completed in March 2022, the spokesperson said.

Stay up to date on all the latest Nation news with The New Indian Express App. Download now

Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.

flipboard facebook twitter whatsapp