polavaram irrigation project

Polavaram Project rejects bills worth Rs 1,086 crore

Officials said Polavaram authorities rejected the bills because of component-wise restrictions and other reasons such as quantities/components not covered in the previous detailed project report.

published on : 11th October 2021

PIP deadline fast approaching, RCE still pending with Centre

State officials say there has been ‘no movement’ in investment clearance proposal; Jal Shakti Min yet to give clearance and send to Union Cabinet for approval

published on : 7th October 2021

Abeyance of stop work order yet to be extended

As the GRMB is set to take over the projects, including PIP, from October 14, the officials said it remains to be seen as to how the resolution would be made. 

published on : 7th October 2021

6,351 PDFs shifted till Sept 14: Polavaram Irrigation Project

26 of 75 resettlement and rehabilitation colonies proposed in first phase completed

published on : 25th September 2021

Govt diverted Polavaram R&R funds, alleges Lokesh

Former ministers N Chinarajappa, Devineni Uma and former MLA Pantham Rajeswari were present.

published on : 2nd September 2021

Jal Shakti Ministry to meet Polavaram Project Authority over discussion on revised cost estimates

Officials to hold another meeting with CWC on pending designs of Polavaram project

published on : 25th August 2021

Andhra govt targets completion of phase-I Polavaram R&R by Oct-end

Entire process linked to completion of pending colonies and release of bills by govt; authorities expect to complete rehabilitation of 75% PDFs by September 

published on : 22nd August 2021

Polavaram hydel power plant tunnel works begin

The officials have also chalked out a plan to expedite the works related to the 960 MW hydel power plant and complete it within the stipulated time.

published on : 7th August 2021

Don’t compromise on Polavaram rehabilitation, resettlement works: CM Jagan

Andhra CM Jagan Mohan Reddy said while the state has not kept any bills related to R&R pending, the Centre is yet to clear Rs 2,300 crores for the Polavaram project.

published on : 20th July 2021

BJP asks Andhra government why R&R works at 21% when Polavaram project is 76% over

Hailing Modi Sarkar at the Centre, BJP state chief Somu Veerraju said gazette notification issued notifying two river water management boards was the best solution for inter-state river disputes. 

published on : 20th July 2021

Polavaram works in full swing: MEIL

In all, 42 out of the 48 radial gates have been installed at the spillway along with fixation of 84 out of 96 hydraulic cylinders.

published on : 14th July 2021

Plan to expedite rehab of Polavaram Project Displaced Families

According to official sources, 5,000 PDFs are ready to be moved currently and the number is set to increase once the financial and compensation obligations are met by the government.

published on : 13th June 2021

Godavari water released for delta via approach channel of Polavaram project

The process began with the removal of the temporary bund at the approach channel to divert water from the river.

published on : 12th June 2021

Expedite Polavaram LARR works: Centre to State

The secretary also reviewed the preparatory measures being taken by the state for the ensuing flood season.

published on : 11th June 2021

Get Rs 1,600 cr Polavaram pending bills released: CM

Jagan asks officials to visit New Delhi, says govt sanctioning money in advance despite financial difficulties as it is a high priority project

published on : 29th May 2021
1 2 >