CHENNAI: The delay in completing the 34.5-km six-laning of Sriperumbudur-Karaipettai section of Chennai-Bengaluru highway, launched eight years ago, continues to cause severe hardship to commuters. The National Highways Authority of India (NHAI) has missed several deadlines for the project and has so far only completed eight of the 17 planned flyovers, bridges and vehicular underpasses along the stretch. NHAI has now set August 2027 as the revised deadline for completing the project.
The existing 15 m wide carriageway narrows to 7.5 m, with traffic diverted to service lanes on either side for nearly 3.5 km to facilitate the construction of vehicular underpasses at Mambakkam and near Sipcot in Sriperumbudur. As a result, vehicles take nearly 60 to 90 minutes to cover the 10 km stretch between Sriperumbudur and Sunguvarchathiram.
Commuters said the prolonged construction work had been causing severe hardship despite the highway being tolled. The situation worsens during weekends and festival seasons when the traffic volume increases. During the recent Deepavali festival, vehicles were stranded in queues stretching up to 9 km between Sunguvarchathiram and Sriperumbudur from November 5 to 10, with congestion persisting throughout the day.
Officials from the NHAI’s Kancheepuram project unit said vehicular underpasses and flyovers at Sunguvarchathiram East and West, Santhavellore, Senthamangalam, Rajakulam, Vedal, Anna Cancer Institute and Ponnerikarai junctions have been completed and opened to traffic.
“Pending works at SIPCOT, Mambakkam, Enathur, Meenakshi Medical College junction, Beemanthangal and other locations are at various stages of execution. The police permit road closures only for limited stretches at a time, which has affected the pace of construction,” an official said.
The official added that there had been minor issues in procurement of soil for the project and that retaining walls had been constructed at two locations. “Of the 34.5 km of pending works, 23.3 km had been completed, while the remaining 11.22 km would be completed by August next year,” he said.
S Sivanesan of Vellore said he experienced bumper-to-bumper traffic for nearly 8 km between Sunguvarchathiram and Rajiv Gandhi Memorial in Sriperumbudur while returning to Chennai from Vellore on November 10. “It took nearly 90 minutes to cover the nine km stretch. During the rainy season, travelling on this road becomes a nightmare,” he said.
Another commuter, S Santhosh Rajan, said road diversions and damaged road surfaces in Sriperumbudur had affected vehicle movement throughout the day. “The dust and soil generated by the highway construction have caused immense hardship to bus passengers and two-wheeler riders. The situation improves slightly beyond Kancheepuram,” he said.
The work to 6-lane the 70 km NH stretch between Sriperumbudur and Walajahpet at a cost of Rs 1,187.6 crore commenced towards the end of 2018.