HYDERABAD:The construction of remaining metro rail pillars at MJ Market will be taken up immediately after the completion of Numaish (All India Industrial Exhibition).
Hyderabad Metro Rail Limited managing director, NVS Reddy along with Additional Commissioner of Police (Traffic) Hyderabad, Jitender on Saturday inspected the ongoing Metro Rail works and the traffic movement between MJ Market-Putlibowli junction and Chaderghat-Moosarambagh junction and said that the water pipeline which is coming in the way of pillar construction will be diverted soon.
The remaining pillars and Metro RoB works at Malakpet will be taken up in a sequential manner in order to facilitate road traffic movement on National Highway. Reddy asked engineers of L&TMRHL and HMR to expedite the construction of two pillars near Chaderghat rotary and complete land acquisition and road restoration in the next 15 days.