46 percent PMGSY road works remains incomplete

Published: 24th December 2016 09:52 PM  |   Last Updated: 24th December 2016 09:52 PM   |  A+A-

By Express News Service

BHUBANESWAR: As the State Government is way behind the annual target of rural road construction under Pradhan Mantri Gram Sadak Yojan (PMGSY), the Centre has asked the State to complete the sanctioned projects by the end of the current fiscal.

With an allocation of Rs 1,650 crore for the state, the Ministry of Rural Development (MoRD) had set a target for construction of 6,200 km of road in 2016-17.

A recent report of the National Rural Road Development Agency (NRRDA) said that the state has so far completed construction of 3,385 km of road providing all-weather connectivity to 715 villages.

"The pace of construction of in your state is very slow and below the average progress at national level. This is still more critical keeping in view the fact that there are 3,111 road works of 12,976.62 km length remained incomplete in the state," said MoRD joint secretary Rajesh Bhusan in a letter to the state government.

Assuring that availability of financial resources will not be constraint, Bhusan said timely release of central assistance will not come in the way of accelerated implementation.

After completion of the 1356 roads sanctioned by the Centre for the state this fiscal, all-weather connectivity will be provided to about 2500 habitations.

After change of funding pattern under the scheme, the Centre has made an enhanced allocation of Rs 1,650 crore for the current financial year against Rs 1,430 crore in the last fiscal, the State has to make a contribution of Rs 1,100 crore.

As per the latest figure, 11,208 habitations of the state are yet to have all-weather road connectivity.

The state government has not been able to provide road connectivity under the flagship infrastructure scheme to 35 villages with more than 1000 population and 165 villages with more than 500 and less than 1000 population.

The state has completed 38,162 km length of road since the launching of PMGSY in 2000-01.

Earlier, the Centre has warned the state government not to reimburse the expenditure made on road projects completed after four years of their approval.

Stay up to date on all the latest Odisha news with The New Indian Express App. Download now
(Get the news that matters from New Indian Express on WhatsApp. Click this link and hit 'Click to Subscribe'. Follow the instructions after that.)

Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.

flipboard facebook twitter whatsapp