The work on the rail overbridge at Mulanthuruthy is in the final stage
The work on the rail overbridge at Mulanthuruthy is in the final stage Photo | T P Sooraj

Long-delayed Mulanthuruthy rail overbridge set to be opened to public soon

Construction of Rs 20.77-crore structure is nearing completion; inauguration next month.
Published on

KOCHI: A serpentine queue of vehicles, especially during peak hours, is a common sight on the Mulanthuruthy-Chengolappadam stretch. For the key route has a railway line cutting across it. While the construction of a rail overbridge (RoB) started over a decade ago, the works got much delayed due to issues like land acquisition.

Finally, the construction of the Rs 20.77-crore structure is nearing completion and is set to be thrown open to the public early next month, providing huge relief to the residents there and also the long-distance commuters travelling from Ernakulam to Kottayam and nearby regions via Chottanikkara.

“Heavy traffic congestion is a usual sight here, especially during the Sabarimala pilgrimage season. A lot of pilgrims visit the Chottanikkara temple and then proceed to the hill shrine. The railway gate (level cross 12) used to be closed at short intervals since it is located on the busy Ernakulam-Kottayam section. Frequent closures for maintenance works made things worse. Hence a RoB was a much-needed facility, the work on which incurred a long delay,” said Reji A C, a local resident.

Interestingly, the railways built the central structure on its land as early as 2013. However, the work on the approach roads, extending 450 m, got prolonged and the construction started only in December 2022.

“Land acquisition was a major issue. Some landowners moved the court over disparities in compensation and the estimate had to be increased. When the process was finally completed in September 2019, the tendering process turned out to be another hurdle. The implementing agency RBDCK had to float the tenders several times as none turned up for a long time before M/s Cherian Varkey Constructions Co Pvt Ltd took up the work,” said Maryamma Benny, president of Mulanthuruthy grama panchayat.

Junction development along with RoB construction

Now the construction of the 450-m-long approach roads has been completed. The RoB has a carriageway, having a width of 7.5 m and a footpath of 1.5 m (only on one side).

“We have also developed the junction (Nelson Mandela Road) where the RoB lands at Mulanthuruthy side to ensure a smooth traffic flow. Now the activities like tarring, side painting and installation of lights remain. We will hand over the bridge to the government before January 25, and the PWD Minister will inaugurate the facility during the first week of February,” an RBDCK official said.

So far, once the railway gate is closed, vehicles that enter from Kottayam and Koothattukulam side and proceed to Chottanikkara, Nedumbassery, Kakkanad and Aluva are forced to wait for a long time. The construction of the RoB was done on a cost-sharing basis between the state government and the Southern Railway. The expense is to be shared in the ratio of 50:50.

X
The New Indian Express
www.newindianexpress.com