The Central Public Works Department (CPWD), which is executing the project, has revised the estimated cost from Rs 11,794 crore to Rs 13,450 crore.

Published: 19th December 2020 01:08 AM  |   Last Updated: 19th December 2020 01:08 AM   |  A+A-

A model of the proposed new Parliament building in New Delhi Saturday Dec. 5 2020. (Photo | PTI)

By PTI

NEW DELHI: The prime minister's new residential complex will have 10 four-storey buildings with a maximum height of 12 metres, according to the government's latest proposal for the redevelopment of Central Vista.

Official sources said that there is "no question of dropping" the proposed new Prime Minister's Office (PMO) from the Central Vista Redevelopment project, after the CPWD did not mention the same in its new proposal before an expert panel of the Ministry of Environment and Forest.

The Central Public Works Department (CPWD), which is executing the project, has revised the estimated cost from Rs 11,794 crore to Rs 13,450 crore.

The prime minister's new residence will be built on a 15-acre plot and it will have 10 buildings and they will have ground plus three floors, the CPWD said in its proposal.

Permissible ground coverage at the prime minister's new residence would be 30,351 square metre, it stated, adding that a building for the Special Protection Group will come up on a 2.50-acre plot.

The Central Vista Redevelopment project also includes the new Vice President's Enclave which will be built on 15-acre land and will have five-storey buildings with a maximum height of 15 metres, the CPWD said in its proposal.

The VP Enclave will have 32 buildings.

Reacting to the CPWD's move to drop the proposed new Prime Minister's Office in its latest proposal, Kanchi Kohli, legal researcher, Centre for Policy Research, said that the documents submitted to the Environment Ministry do not give any justification on why some plots or offices have been excluded or why the costs have increased despite such exclusions.

"But equally important is the CPWD's answer to whether any alternatives to the present proposal were considered is a "No". The study of such alternatives is required to be done before seeking environment clearance," Kohli said.

The CPWD's proposal for terms of reference, which is a step before the environment clearance, was discussed by the Environment Ministry expert appraisal committee (EAC) on Thursday.

The EAC had approved the CPWD's proposal to construct a new Parliament Building earlier this year.

The redevelopment project of Central Vista -- the nation's power corridor -- also envisages a new triangular Parliament building, a common central secretariat and revamping of the three-km-long Rajpath, from Rashtrapati Bhavan to India Gate.



Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.

flipboard facebook twitter whatsapp