Remote villages in ASR district, Andhra Pradesh remain in darkness

Villages yet to be connected to power grid despite erection of electric poles and creation of other infrastructure
Tribals of Buruga and Chinna Konela staged a protest for electricity
Tribals of Buruga and Chinna Konela staged a protest for electricity Photo I Express
Updated on
2 min read

VISAKHAPTANAM: Buruga and Chinna Konela, two remote tribal hamlets in Rompalle Panchayat under Anantagiri mandal of Alluri Sitarama Raju (ASR) district, continue to wait for electricity, despite recent developments in their villages. While electric poles and transformers have been installed, the final steps-connecting the power supply and installing metres-remain incomplete, leaving the villagers without access to power.

For the Kondh tribes who inhabit these villages, the absence of electricity poses significant challenges. Without lights after dark, they rely on torches made from wooden sticks to navigate their surroundings, which are frequented by wild animals, including snakes. The lack of electricity also means that many daily activities must end before sunset, especially for villagers who depend on Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) work and daily wage labour at local brick kilns.

The villagers have repeatedly protested the delay in electrification. A few months ago, families in Buruga village faced the loss of livestock when a tiger killed their cattle. Despite notifying the Forest Department, they have yet to receive compensation for the incident.

The electrification process began after continued demands from the community, with the installation of poles and transformers marking significant progress. However, more than two weeks have passed since, and the final steps remain pending. The delay has frustrated the villagers, who are eager to see the completion of the project.

“The electricity connection brings us access to many basic needs, including drinking water and safety after dark. Without power, we cannot install tap water systems in our homes,” they explained, adding, “We are happy to see the officials speeding up the work, but we urge them to finish it so we can have electricity in our homes.”

Ravi Kumar, Executive Engineer (Construction & Operation) at Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL) Paderu, explained the reason for the delay, saying, “Due to recent heavy rains, the roads were inaccessible. We have completed most of the work and are only left with installing metres in the households. The villages will have electricity within a week.”

For the villagers, electricity represents more than just light. “It will allow our children to study and play after sunset, and it will help the elderly move around safely at night. We hope this final hurdle is cleared soon,” they added.

The promise of electricity has sparked hope, but the wait continues. The villagers expressed optimism that their long-standing demand will soon be met, improving their quality of life.