Fund sanctioning delayed, uncertainty looms over Phase Two of Western Ring Road project

The work began in August 2023 and the state government had earlier sanctioned Rs 320 crore for land acquisition for all three phases of the project.
National Highway workers engaged in final works of Outer ring road near Milekal in Coimbatore on Saturday.
National Highway workers engaged in final works of Outer ring road near Milekal in Coimbatore on Saturday.Photo | S Senbagapandiyan.
Updated on: 
2 min read

COIMBATORE: Even as the first phase of the much-awaited Western Ring Road (WRR) project in Coimbatore has been almost completed, uncertainty over fund sanction has delayed the commencement of the second phase, raising concerns over prolonged traffic bottlenecks on the city's western outskirts.

The State Highways Department is yet to receive administrative sanction and funds from the Tamil Nadu government for Phase Two of the project, despite having submitted the proposal several months ago. Officials said the delay has stalled preparations for the next stretch of the ring road, which is critical to ease congestion in fast-growing residential and commercial areas.

Phase One of the WRR, spanning nearly 11.80 km from Mylkal to Madampatti, is almost over. Road furnishing works such as white line markings, installation of reflectors and warning sign boards, and fixing of streetlights are currently under way. In sections where work has been fully completed, motorists have already started using the road.

The first phase, implemented at an estimated cost of Rs 250 crore, runs through Madukkarai, Sundakkamuthur, Perur Chettipalayam, Theethipalayam and Madampatti. The work began in August 2023 and the state government had earlier sanctioned Rs 320 crore for land acquisition for all three phases of the project.

According to the original timeline, the Highways Department had planned to complete Phase One by August 2025 and begin Phase Two, a 12.10-km stretch from Madampatti to Somayampalayam, in September 2025. However, delays in completing the first phase pushed back the schedule, and the absence of funds has now compounded the delay.

Phase Two, which will pass through Perur, West Chithirai Chavadi, Kallikanaicken Palayam, Vadavalli and Somayampalayam, is estimated to cost Rs 368 crore. Officials said the proposal seeking funds for this phase was sent to the government during September-October last year, but no clearance has been granted so far.

"Phase One is almost complete and only finishing works like road markings and signboard installation are left. We submitted the proposal for Phase Two several months ago, but we are yet to receive administrative sanction and funds. Without this, we cannot start the work," a senior State Highways Department official told TNIE.

The official also revealed that the state government plans to execute Phase Two through the newly formed Tamil Nadu State Highways Authority (TANSHA). Sources indicated that the next phase is likely to be taken up only after the Assembly elections.

The government will also take a final decision on toll collection for the entire 31-km Western Ring Road after all three phases are completed. For now, officials clarified that no toll will be collected on the first 11-km stretch, which is expected to be inaugurated soon.

Once completed, the Western Ring Road is expected to significantly reduce traffic congestion in Coimbatore by diverting heavy and long-distance vehicles away from the city, improving connectivity and easing pressure on arterial roads.

Related Stories

No stories found.

X
The New Indian Express
www.newindianexpress.com