‘ Kakinada-Vizag-Srikakulam gas pipeline to be completed by 2024’: Rameswar Teli

Previously, works between Kakinada and Visakhapatnam were to be completed by June 30, 2021 and by June 30, 2022, between Vizag and Srikakulam, Teli said. 

Express News Service

VIJAYAWADA: Kakinada-Vizag-Srikakulam natural gas pipeline will be completed by June 2024, Minister of State for Petroleum and Natural Gas Rameswar Teli informed Rajya Sabha in a written reply to a query raised by YSRC MP V Vijayasai Reddy.

He pointed out that though the deadline was June 30, 2022, it was extended to June 30, 2024, on the request of Andhra Pradesh Gas Distribution Corporation (APGDC).

The minister explained that that the Natural Gas Regulatory Board made Andhra Pradesh Gas Distribution Corporation (APGDC) an authorised organisation for construction and monitoring of Kakinada-Vizag-Srikakulam natural gas pipeline in 2014. 

Previously, works between Kakinada and Visakhapatnam were to be completed by June 30, 2021 and by June 30, 2022, between Vizag and Srikakulam, Teli said. 

However, due to the Covid pandemic, problems faced during rainy season for construction of pipeline, delay in release of funds, the APGDC requested the Board for an extension till June 2024, the minister elaborated. 

Iran seizes third container ship in Hormuz after Trump extends ceasefire indefinitely

Gyanesh Kumar is the 'logical discrepancy, national shame': Kapil Sibal slams CEC over 'abuse of power' in Bengal

Lodhi community men assault physically challenged Dalit groom during pre-wedding procession in MP

TMC alleges BJP misused Railways for voter transport to West Bengal ahead of first phase elections, moves EC

Delhi HC refuses to entertain PIL on alleged LPG black marketing, asks petitioner to approach government

SCROLL FOR NEXT