‘ Kakinada-Vizag-Srikakulam gas pipeline to be completed by 2024’: Rameswar Teli

Previously, works between Kakinada and Visakhapatnam were to be completed by June 30, 2021 and by June 30, 2022, between Vizag and Srikakulam, Teli said. 

Express News Service

VIJAYAWADA: Kakinada-Vizag-Srikakulam natural gas pipeline will be completed by June 2024, Minister of State for Petroleum and Natural Gas Rameswar Teli informed Rajya Sabha in a written reply to a query raised by YSRC MP V Vijayasai Reddy.

He pointed out that though the deadline was June 30, 2022, it was extended to June 30, 2024, on the request of Andhra Pradesh Gas Distribution Corporation (APGDC).

The minister explained that that the Natural Gas Regulatory Board made Andhra Pradesh Gas Distribution Corporation (APGDC) an authorised organisation for construction and monitoring of Kakinada-Vizag-Srikakulam natural gas pipeline in 2014. 

Previously, works between Kakinada and Visakhapatnam were to be completed by June 30, 2021 and by June 30, 2022, between Vizag and Srikakulam, Teli said. 

However, due to the Covid pandemic, problems faced during rainy season for construction of pipeline, delay in release of funds, the APGDC requested the Board for an extension till June 2024, the minister elaborated. 

'We need constructive change': Students, parents at CJP protest seek accountability in education system

Karnataka Cabinet row: Ramalinga Reddy has withdrawn his resignation, claims Surjewala

'TVK in power due to our grace': Stalin asks DMK workers to pledge end of Vijay-led govt

Congress distances itself from CJP protest even as Opposition allies rally behind movement

Doctor booked for rape, forced abortion of Dalit woman employee in UP's Bijnor

SCROLL FOR NEXT