BBMP chief sets March ’26 deadline for Ejipura Flyover

437 of 762 segments installed; land hurdles near St John’s cleared, night work under way to avoid traffic disruption

Express News Service

BENGALURU: Bruhat Bengaluru Mahanagara Palike (BBMP) Chief Commissioner Maheshwar Rao has set a deadline of March 2026 for the completion of the Ejipura flyover work. During an inspection at the segment casting yard at Sakalavara on Bannerghatta Road on Friday, he directed officials to accelerate the pace of construction.

The 2.38-km flyover on Ejipura Main Road will require 762 segment castings. Of these, 437 have already been installed, with 325 remaining. Rao directed officials to cast and install 45 segments per month to meet the deadline.

He also instructed that the segment casting be completed by the end of this year. He also stated that the land acquisition issues near St John’s Hospital and hostel, two key points along the route, have been resolved following a meeting with stakeholders.

Chief Engineer Raghavendra Prasad said, “The implementation plan is ready, and work is proceeding swiftly despite traffic constraints. Segment erection is being carried out between

11 pm and 5 am to minimise disruption. Footpath work is nearly complete, and the lower portion of the flyover has been asphalted in several stretches. Drainage and median work is also under way.”

High energy cost transfer 'inevitable' to users: Finance ministry

Poll of Polls: DMK may hold Tamil Nadu, Opposition surge seen in Kerala, Bengal

Trump warns Iran blockade could last months, sending oil prices soaring

West Bengal records over 91.66 per cent voter turnout amid sporadic violence

Putin, Trump discuss Iran war, Ukraine in phone call, says Kremlin

SCROLL FOR NEXT