Vijayawada

Coastal belt railway expansion by 2020-21

Expansion of the rail network between Vijayawada and the coastal belt, where the single line is being electrified and doubled, is expected to be complete by 2020-21.

From our online archive

VIJAYAWADA: Expansion of the rail network between Vijayawada and the coastal belt, where the single line is being electrified and doubled, is expected to be complete by 2020-21. At present, the Vijayawada-Gudivada-Bhimavaram-Narsapur and Gudivada-Machilipatnam; Bhimavaram- Nidadavolu railway lines are single lines and non- electrified.

Indian Railways took up the doubling and electrification project on the lines, for a distance of 221 km, in order to encourage the development of the coastal belt of Andhra Pradesh, in 2011-12.The estimated cost of the project was Rs 1428.70 crore. 

The project was planned to be executed in five phases. Till now, 28.66 lakh cubic meters of earthwork has been completed. As many as 369 minor bridges have been completed. Work in another 54 minor bridges is currently in various stages of progress.

The expansion project

There is 50 per cent cost-sharing by the State government. Rail Vikas Nigam Ltd. is executing the project. The expenditure incurred on this project during the last 4 years up to March 2019 is Rs 623.06 crore and during 2018-19 is Rs 226.65 crore. Expenditure incurred till now is Rs 849.71 crore

Cong demands PM Modi's resignation for 'match-fixing' polls through CEC; demands suspension of SIR

Asian Games 2026: Shooter Neeru ends India's wait, bags historic gold in trap discipline

One Assam Rifles jawan killed, four injured in suspected militant attack in Arunachal's Changlang district

Jaishankar flags US lack of understanding on cross-border terror concerns, says it impacts bilateral ties

SC to hear plea raising doubts over CEC Gyanesh Kumar's decisions next week