Spaces under Vijayawada's Benz Circle flyover-1 to turn green soon

The civic body is planning to develop greenery in the spaces under the Benz Circle flyover-1 as several trees were axed to execute the project causing damage to the environment.

Sistla Dakshina Murthy

VIJAYAWADA: Taking a cue from the greenery developed in spaces under Kanaka Durga flyover, the Vijayawada Municipal Corporation (VMC), along with National Highway Authority of India (NHAI), has decided to replicate the same on the newly-inaugurated Benz Circle flyover-1.

Designs in this regard were readied by the civic body at an estimated cost of Rs 2.75 crore and officials set a target to complete the project by March 2021.

The civic body is planning to develop greenery in the spaces under the Benz Circle flyover-1 as several trees were axed to execute the project causing damage to the environment.

Keeping this in view, the officials have readied designs to develop greenery and a park to prevent the space being encroached by the traders and make it accessible for all the sections of public.

As part of the plans, designs readied by the VMC to develop greenery on a 1.1 km stretch from pillar number 1 to 43. The same has been approved by the NHAI and tenders in this regard will be finalised on November 3.

VMC Additional Director (Horticulture) J Jyothi said that as per plans, initially, greenery will be developed in the spaces under the flyover excluding the stretch between SVS Junction and Bharathi Nagar.

Due to space constraint, play equipment will not be installed on the green belt, benches will be arranged and a walking track will be developed for the convenience of joggers, while fencing will be arranged by the NHAI, she said, adding that the spot located adjacent to the NH-16 will be easily accessible to all sections of public. 

“The tenders will be finalised on November 3. The firm which gets eligibility should commence the project works from the third week of November and complete it by February-end,” Jyothi explained.

TN polls 2026: How Sonia and the seniors stopped Congress-DMK ties from fracturing

LIVE | West Asia conflict: Iran vows 'eye for eye' response to attacks; UAE shuts largest refinery after drone strikes

Air India, Air India Express ticket prices to rise as fuel surcharge imposed amid West Asia war

Indigo CEO Pieter Elbers resigns with 'immediate effect' three months after airline faced massive crisis

Fewer dishes, dosas could be worst hit?: Restaurants across India battle LPG shortage

SCROLL FOR NEXT