Govt crackdown soon on developers of delayed power projects: Union Minister

Singh also said that until battery energy storage becomes viable, India would have to add thermal power capacity to meet the demand.

PTI

NEW DELHI: Power and New & Renewable Energy Minister R K Singh on Thursday said the government will crack down on developers of power projects, who miss the scheduled commercial date of operation or deadline to complete the project.

Addressing a CII conference Singh said the electricity generation capacity addition is a big challenge, as people are sitting on several projects won under the bidding process.

Singh said that all these projects (power projects) are won under the bidding process and if they miss the SCOD (scheduled commercial date of operation or deadline to complete the project), then the developer will be banned from participating in project bidding for one year.

On the second such incident, the developer will be banned for five years, Singh said, adding that he is going to put this (rule) in (policy).

Power project developers are waiting for demand to grow but this will not happen, he said.

Singh also said that until battery energy storage becomes viable, India would have to add thermal power capacity to meet the demand.

At present the battery storage is Rs 10 per unit and the energy rate is Rs 2.30, he explained.

He also said that he is pushing the case for another production-linked incentive scheme for grid-scale battery energy storage.

Visas a 'sovereign' matter, says MEA as Tharoor alleges 115 Bharat Summit speakers barred

At least 26 killed as minibus collides head-on with container truck near Kaziranga National Park in Assam

What IAF's Gajraj landing at Nyoma, the border with China, means

Microsoft restores parts of India, APAC infrastructure after global service disruption

'Proof against Modi on my phone': Rahul alleges PM tapping device, renews debate call