A section of the Pink Line stretch where construction is under way | File pic 
Kochi

40% civil work of Kochi Metro Pink Line completed; five stations to be operational by June 2025

Piling progress is nearing 80%; of the 470 piers planned along the corridor, 175 have been constructed so far

Ronnie Kuriakose

KOCHI: Putting behind the delays of 2025, work on the Kochi Metro phase 2 project, also known as the Pink Line, has picked up pace in the new year with over 40% of the civil work completed. Foundation-related activities are nearing their final stages, an official with the Kochi Metro told TNIE.

The Pink Line is an 11.2-kilometre elevated metro rail corridor with 11 stations, connecting the city heartland with its eastern residential suburbs and key business hubs such as Infopark, CSEZ, and Kinfra. Five of those stations are slated to become operational by June 2026 and the remaining stretches by the end of the year.

“The work has been expedited to make up for delays encountered last year due to some setbacks. We still intend to see the work completed by the June deadline for the first five stations, and by the end of the year for the rest of the line,” the Kochi Metro official said.

Piling, which forms a major portion of the groundwork, is close to completion. Of the 2,027 piles required for the project, over 1,450 have already been completed. “The piling progress is nearing 80%,” the official highlighted.

The construction of piers is also under way. Of the 470 piers planned along the corridor, 175 have been completed so far. This includes 144 viaduct piers and 32 station piers. In terms of pile caps, 477 units are required, of which 257 have been completed and made ready. “These pile caps are pre-fabricated at our yard and transported to the site for installation, helping speed up construction,” the official said. Work has also begun on pier caps, which sit atop the piers and support the girders.

Of the 62 pier caps needed, 36 have been completed. Meanwhile, girder launching, one of the most visible stages of metro construction, is progressing along select stretches.

“The project requires 488 precast girders, of which 149 have been completed. In addition, 337 pier caps are required for girder placement. Of those, 177 are ready. In terms of high girders, of the 544 needed, 108 have already been cast and installed,” he added. Station-related work is also progressing well at Alinchuvadu, Vazhakala, CSEZ, Kinfra, Chembumukku, Civil Station, Infopark, Padamugal and Palarivattom, with piling completed at six of these locations.

“The superstructure construction will begin soon,” the official said. The original deadline for the completion of the Pink Line was the end of 2025. After a few setbacks, this was revised to December 31, 2026. However, Kochi Metro decided to open the first five stations – from Palarivattom to Padamugal — by June 30. “We are determined to keep this deadline,” the metro official stressed.

Will Pink Line services extend to MG Road or stop at JLN?

On operations, Kochi Metro authorities said traffic demand studies are essential before determining whether the Pink Line services would terminate at the JLN Stadium interchange or be extended further towards the city centre. “We will take a call on the route once traffic demand needs are analysed. If the Pink Line services are to be extended to MG Road, rather than terminating at JLN Stadium station, then new trains will be required,” the official said.

Activists claim Iran has aired at least 97 coerced confessions from protesters, often after torture

Fire breaks out at BJP MP Ravi Shankar Prasad's official residence in Delhi

Crane collapse at China-backed railway project derails train in Thailand, killing 22

Another scam rocks Sabarimala: Rs 35 lakh fraud unearthed in ‘Adiya Sishtam Ghee’ sale at temple

None of Indian private space firms insured satellites on PSLV

SCROLL FOR NEXT