After delay of eight months, Thirumangalam water scheme to be ready in May

An official from the Thirumangalam Municipality attributed the delay to multiple factors, including issues related to departmental clearances.

Saravanan MP

MADURAI: The new drinking water supply scheme for Thirumangalam municipality implemented at a cost of Rs 52.54 crore is expected to be completed only by May 2026, facing a delay of more than eight months from its original deadline, due to multiple factors, including issues related to departmental clearances.

The project, which was launched on January 22, 2024, was initially scheduled to be completed by October 2025. Residents have expressed disappointment over the slow progress of the project. K Moorthy, a resident of Thirumangalam, said that the town had been awaiting an improved water supply scheme for several years.

“In early 2020, senior officials and a few politicians from Thirumangalam municipality announced a new water supply scheme for the town estimated at Rs 40 crore. But for nearly two years there was no progress. Later, in November 2023, it was revealed that a revised project would be launched with an increased estimate of Rs 52.54 crore, drawing water from the Vaigai river near Mullipallam village,” he said.

Another resident, A Sathish, pointed out that the project proposal included the construction of five overhead tanks (OHTs) within Thirumangalam town. “Two overhead tanks were constructed in early 2024 along the Thirumangalam–Madurai Main Road and Sholavandan Main Road, but they are still incomplete,” he said.

He further alleged that pipeline works along the Thirumangalam–Virudhunagar Main Road stretch of about three kilometres have not been taken up over the past two years.

Meanwhile, an official from the Thirumangalam Municipality attributed the delay to multiple factors, including issues related to departmental clearances.

“The project began on January 22, 2024, but actual works commenced only in the second week of June 2024. There were issues related to the pumping station and pipeline works involving the Public Works Department, which had to be resolved,” the official said.

He also added that permission from the forest department was required for laying pipelines across a 600-metre stretch near a reserve forest in Sholavandan.

According to the official, around 90% of the pipeline works have now been completed. Recently, permission was also obtained from the State Highways Department to lay pipelines along the Thirumangalam–Madurai Main Road for a distance of three kilometres.

LIVE | Trump says Iran's Kharg Island bombed as Tehran hits back with attack on US mission, warns oil sites next

Government asks restaurants to switch to coal, households to PNG as LPG crisis deepens

Mankind's fate at the hinge of history

RSS's Pratinidhi Sabha discusses outreach to Kerala's Christian, Muslim communities ahead of polls

Draft bill moots transgender definition overhaul

SCROLL FOR NEXT