Bengaluru: Signalling tests for first driverless train begin on Yellow Line

A scheduled running test could take a week and an independent safety assessment by a third party could take another ten days, the official elaborated.

Express News Service

BENGALURU: The Dynamic signalling tests for the first driverless train began between RV Road and Bommasandra (Yellow line) on Monday, said a senior BMRCL official. Preliminary activities in this connection were on since June 13. “As planned earlier, we began the Dynamic Signalling tests at 3 pm today. It requires a series of tests to be completed and will take around 2.5 months,” he said.

Detailed data-checking needs to be done which will take upto 45 days. “This will be followed by the Integration Test which takes around 15 days. Multiple train tests involving running of trains in opposite directions on each of the tracks will take another 10 days,” he explained.

A scheduled running test could take a week and an independent safety assessment by a third party could take another ten days, the official elaborated. The line is expected to open for commercial operations by December 2024.

Indian captain hailed as 'true hero' for fighting off co-pilot who tried to crash Flydubai flight

Punjab Congress rift: Amrinder Warring offers to resign as new state chief is likely

Mahanadi water dispute: What are the issues holding up a settlement

A united INDIA bloc closes ranks on ECI row as it charts next political and legal moves

Modi, Trump hold first call since Russia and Iran sanctions law as trade talks continue