Bengaluru: Signalling tests for first driverless train begin on Yellow Line

A scheduled running test could take a week and an independent safety assessment by a third party could take another ten days, the official elaborated.

Express News Service

BENGALURU: The Dynamic signalling tests for the first driverless train began between RV Road and Bommasandra (Yellow line) on Monday, said a senior BMRCL official. Preliminary activities in this connection were on since June 13. “As planned earlier, we began the Dynamic Signalling tests at 3 pm today. It requires a series of tests to be completed and will take around 2.5 months,” he said.

Detailed data-checking needs to be done which will take upto 45 days. “This will be followed by the Integration Test which takes around 15 days. Multiple train tests involving running of trains in opposite directions on each of the tracks will take another 10 days,” he explained.

A scheduled running test could take a week and an independent safety assessment by a third party could take another ten days, the official elaborated. The line is expected to open for commercial operations by December 2024.

Mamata condemns attack on judicial officers amid SC rap, says BJP 'plotting' unrest for President’s rule

Iran vows 'crushing' attacks on US after Trump's 'back to Stone Ages' threat

Rahul Gandhi releases Congress manifesto for Assam elections, with focus on 11 sectors

AAP drops Raghav Chadha as Rajya Sabha deputy leader, names Ashok Kumar Mittal

Vijay alleges conspiracy in Karur tragedy, says election should lead to 'whistle revolution'

SCROLL FOR NEXT