Four-lane underpass on Bengaluru Old Airport Road to open to traffic by January 2027

The remaining retaining wall construction towards HP Petrol Bunk side has been completed, and soil excavation and underground work is nearing completion.

Mohammed Yacoob

BENGALURU: The 300-metre four-lane underpass at Wind Tunnel Road, National Aerospace Limited and Challaghatta Junction on Old Airport Road, started earlier this year, is now almost 80 per cent complete, as earth movers have made space for precast structures. According to engineers, the underpass, being built at a cost of Rs 19.5crore, is likely to become operational by January 2027.

The remaining retaining wall construction towards HP Petrol Bunk side has been completed, and soil excavation and underground work is nearing completion. The contractor had been given a January deadline.

“Workers are facing challenges at the site, as there is a 300-diameter Bengaluru Water Supply and Sewerage Board (BWSSB) water pipeline. We are coordinating with BWSSB engineers to shift the line and other utilities. By next week, precast boxes will be erected on one side and by the end of December, the process will be completed, and traffic will be allowed.

In January, the other side of the box will also be completed, and traffic will be moving on both sides,” said an engineer at the site.Work should have started in 2023 under the erstwhile Bruhat Bengaluru Mahanagara Palike’s (BBMP) Project Wing, but Bengaluru Traffic Police denied permission, citing heavy VVIP movement on the stretch as they take Old Airport to catch chartered flights.

With the 300-metre four-lane project nearing 80 per cent completion

“From the Governor to the CM, VVIPs take this route, Central ministers also arrive at Old Airport to reach Lok Bhavan to meet the Governor and attend other events, hence, permission was denied.

However, in May this year, Chief Commissioner M Maheshwar Rao directed officials to take up work, as the traffic department finally gave its green signal, with intervention from the Urban Development Department. We had to follow the condition of partial road cutting while allowing traffic, now we have completed 75 to 80 per cent of the work,” said a site engineer from Bengaluru Central City Corporation.

Chief Commissioner Maheshwar Rao inspected the works and directed officials to use cutting-edge technology and try to complete work in three months’ time in May; however, the project was delayed due to utilities. Rao also directed officials to carry out work in three shifts, using additional machinery, and complete it at the earliest.

Three bills, 850 Lok Sabha seats and 25-year freeze: Centre's plan for delimitation-linked women's quota

Cabinet okays delimitation-linked women quota bill; NCP(SP) to 'back' it, DMK firm on TN share; Oppn to huddle

Bombay HC allows Nov 30 Tata Sons board meet amid Tata Trusts' challenge to Chandra's reappointment

Thirupparankundram Deepam row: Vijay holds high-level meeting, CRPF personnel land in Madurai

TVK MLA Arul Vignesh arrested over alleged obscene messages to Kallakurichi Collector