Imtiaz said that 49 per cent of construction works have been completed so far.  
Vijayawada

Ready Benz Circle flyover-II by November: District Collector A Md Imtiaz

The total length of the Benz Circle flyover-II is 1.7 km, in which approach road will be constructed for a length of 0.77 km.

Express News Service

VIJAYAWADA: District Collector A Md Imtiaz has directed officials concerned to complete Benz Circle flyover-II works by November. 

The Collector accompanied by the officials of National Highway Authority of India (NHAI) and electricity department conducted a ground level inspection on Saturday to take stock of the progress of works.

Speaking on the occasion, Imtiaz said that 49 per cent of construction works have been completed so far. 

The NHAI and contractors should coordinate with each other for speedy completion of flyover works.

The total length of the Benz Circle flyover-II is 1.7 km, in which approach road will be constructed for a length of 0.77 km.

So far, 56 pillars of the flyover have been constructed, but structural work has been completed only for eight pillars. 

Imtiaz instructed the officials concerned to speed up the construction works of the flyover-II with advanced technology.

The Collector said that NHAI will provide funds to the electricity department to relocate the electric poles which are hampering flyover works. 

BCI chair apologises over NALSAR ban order, says students 'don't require anyone to decide for them'

Jharkhand protest: Students to burn Soren and Rahul effigies, gherao CM's residence Aug 20

Tamil Nadu BJP chief's 'ask mother' jibe at CM Vijay triggers political backlash

SHANTI Act draft rules set operator liability, financial safeguards for private nuclear push

PoK would be protesting to reunite with J&K had Article 370 stayed: Omar Abdullah in I-Day speech

SCROLL FOR NEXT