The project is meant to be a five-year continuous initiative aimed at cleaning the 320km coastline of Karnataka Photo | Express
Karnataka

Two years on, Karnataka govt's K-Shore project yet to take off

Experts working closely with the government said there was no need to announce this project.

Bosky Khanna

BENGALURU: The state government’s ambitious Karnataka – Strengthening Coastal Resilience and the Economy (K-Shore) project, which was announced in 2024, is yet to take off. Officials in the departments of forests, environment and ecology admitted to the delays in the execution of the project.

“The project’s execution has been delayed. Before implementation, it is important to get everyone onboard, which is taking time. The government approvals also take a long time,” said a senior environment and ecology department official, not wanting to be named.

While clearing the project, the World Bank, which has funded Rs 840 crore for its execution, made a condition before the state government to show that 30% of the annual outlay of the work is ready for immediate implementation, and that it is approved by the department of economic affairs.

Experts working closely with the government said there was no need to announce this project. “There are already many rules and orders issued in the past, such as fisheries department order to take back nets, solid waste management rules of 2016, extended producer responsibility rules, water treatment rules and Swachch Bharat Abhiyaan. The project has been announced before any of these were implemented,” said an NGT expert.

For the effective execution of the project, thorough coordination among all government departments is required. Furthermore, the state government has also partnered with the ministry of environment, forests and ecology and Tamil Nadu government for the project’s implementation.

The project is meant to be a five-year continuous initiative aimed at cleaning the 320km coastline of Karnataka, particularly making it free of plastic and other pollutants, as well as promoting sustainable development. It also includes material recovery facility, mangrove plantation, assisted natural generation and regeneration, creation of coastal shelterbelts and protection of myristica swamps.

Clearing of plastic and pollutants in the 5-10km coastline, particularly ghost nets, is also listed. Besides the Blue Flag beaches, the project will cover all the beaches in Uttara Kannada, Udupi and Dakshina Kannada.

“The K-Shore project has just started this financial year. It was approved last year by the World Bank. Discussions with fisheries, rural development and panchayat raj, panchayats and other coastal agencies are under way,” said Principal Chief Conservator of Forests Meenakshi Negi.

US judge strikes down Trump's $100,000 fee for H-1B visas, calls it unlawful tax

Knives out at INDIA bloc meeting as allies turn heat on Congress over lack of coordination, DMK exit

TMC rebellion reaches Lok Sabha: 20 MPs write to Speaker Om Birla expressing desire to join NDA

Manipur: Thousands rally in Imphal demanding NRC updation before Census exercise

Eight workers killed, several injured at Visakhapatnam Steel Plant as molten iron spills

SCROLL FOR NEXT