A portion of Indravati's right canal extension filled with water Photo | Express
Odisha

Odisha: 76 villages in Kalahandi finally get irrigation water after 20 years

The extended Indravati right canal now provides irrigation to 9,000 hectares of land in Bhawanipatna and Kesinga blocks, benefiting 76 villages.

Express News Service

BHAWANIPATNA: After a long wait of 20 years, 76 villages in Bhawanipatna and Kesinga blocks of Kalahandi district have finally received irrigation water from the Indravati project during the current kharif season.

This was made possible through the extension of the Indravati right canal that stretches 88 kilometers from Mukhiguda to Badaphunda, with the recent extension adding another 44 kilometers from Badaphunda to Goudtula.

Construction of the canal extension began in 2002-03 and was completed in 2014-15, aiming to irrigate 15,260 hectares of land. However, due to insufficient hydraulic pressure in the main canal and erosion in the extension canal caused by prolonged delay, water could not be released until now.

This season, 9,000 hectares of land across 55 villages in Bhawanipatna block and 21 villages in Kesinga block have received irrigation for the first time through the canal extension.

Executive engineer of the Indravati right canal, Rajkumar Behera, confirmed that water reached the targeted fields after completing concrete lining work up to 44 kilometers of the main canal and repairing the extension canal. The entire targeted area of 15,260 hectares is expected to benefit soon, he added.

‘Defaming India at international platforms will not help Rahul Gandhi come to power’: Amit Shah

Megaspeed says Alice Huang left in 2025 as company conducts internal probe over Nvidia fallout

England beats Australia by 135 runs to level the ODI cricket series 1-1

Eight injured as under-construction hotel building partially collapses in Delhi's Paharganj

Delhi's AQI improves to 'poor' at 290, first time since November 10