Delay in Ennaikolpudur project irks farmers in Dharmapuri

This project could have been completed years ago, but due to delay in land acquisition, the project has been put on hold.

Express News Service

DHARMAPURI: Farmers have expressed concern over the unexpected delays and challenges in land acquisition in the Ennaikolpudur-Thumbalahalli project, which has led to the completion of only 62% of the works so far.

The Ennaikolpudur-Thumbalahalli scheme was a project proposed to tackle drought in parts of Karimangalam, by diverting excess water from the Thenpennai river to Thumbalahalli dam. The project was proposed at the cost of Rs 175 crore and later excess funds were sanctioned taking up the project cost to Rs 233 crores. Under this project, a 50-kilometer canal system would be constructed to supply water to 34 lakes and one dam across the Palacode and Karimangalam areas in Dharmapuri, as well as lakes in Krishnagiri.

Speaking to TNIE, A Murugesan from Karimangalam said, "Under the Ennaikolpudur-Thumbalahalli project, the water from Thenpennai would be transported by the 22.67 km left canals which is being constructed. The project would benefit over 3,500 acres of cultivation lands in Karimangalam. The right canal would provide about 207.50 million litres of water and the left canal would provide 161 million litres of water. Further, several aqueducts are also under construction to transport water between hills. This project could have been completed years ago, but due to delay in land acquisition, the project has been put on hold. Now, with the land acquisition completed, we hope the project will speed up."

B Chinnasamy, a farmer from Karimangalam said, "This year, the impacts of El Nino had crippled over 13,000 hectares of crops across the district and Karimangalam alone has lost of 3,500 hectares of crops due to monsoon failure. This could have been avoided, if the Ennaikolpudur-Thumbalahalli project was completed in the scheduled time frame by 2023. Most of the project lies in Krishnagiri district and opposition by the farmers there had also led to the delay. Now, with all the problems resolved, we hope the project will be completed soon."

When TNIE reached out to engineers in the PWD (WRD) they said, "At present, over 62% of the canals and aqueduct works are completed, the land acquisition was met with much opposition in Krishnagiri district and so it was delayed. Previously for acquisition, Rs 89 crores were sanctioned, but these funds were not enough, so we have sought the state government for additional funding. Furthermore, in the lands already acquired, we have begun construction and soon the project will be completed."

Asian Games 2026: Kumkum Mohod wins India's 1st ever recurve individual gold medal, earns Olympic quota

FlyDubai co-pilot who nearly crashed plane was barred from flying by Oman over extremism concerns

Kerala CM V D Satheesan faces heat over style of functioning, high command set to step in

Hockey legend Pargat Singh replaces Amarinder Warring as Punjab Congress chief

Tale of perseverance & grit: Lovlina regains spark with golden punch in Asian Games