A total of 23 tunnel boring machines will be used to build the extensive network of underground tunnels in Phase 2 of Chennai Metro Photo | Express
Chennai

Work on 7.8 km metro tunnel starts with launch of boring at Chennai's Kolathur

The 7.8km stretch along with five underground stations from Kolathur Ramp to Nathamuni Ramp are being executed through Tata Projects limited, according to a release.

Express News Service

CHENNAI: The work on the 7.8km underground tunnel under corridor 5 began on Wednesday with the launch of the tunnel boring machine (TBM) ‘Kurinji’ which will bore a 246m tunnel from Kolathur Ramp towards Kolathur Station (upline) and is expected to finish by June.

The TBM will then be retrieved and relaunched from the south shaft to tunnel towards Srinivasa Nagar (1.06 km). The second TBM, Mullai, is expected to arrive by the end of March and will begin tunnelling adjacent to Villivakkam Railway Station towards Villivakkam Bus Terminus (603m).

The remaining two TBMs will be launched based on site readiness, according to a CMRL release. The 7.8km stretch along with five underground stations from Kolathur Ramp to Nathamuni Ramp are being executed through Tata Projects limited, according to a release.

Additional chief secretary (special initiatives) Dr K Gopal along with Chennai Metro director (projects) T Archunan and other officials visited the site. The work on the stretch was delayed by a year due to the late awarding of tenders.

Trump says US will be out of Iran 'pretty quickly' as Tehran rubbishes claims of seeking ceasefire

West Asia conflict: PM reviews supply chains, price stability, diversification for LPG and LNG in CCS meeting

Amazon's cloud computing facility in Bahrain hit in Iranian strike, reports Financial Times

Bengal elections: Voters whose names were deleted from electoral rolls after SIR, gherao judicial officers in Malda

IndiGo revises fuel charges by up to Rs 950 for domestic flights after jet fuel price hike

SCROLL FOR NEXT