The project remains on track, with plans to open the corridor for passenger services by late 2025, officials said.  (Photo | Express)
Chennai

CMRL completes grade separator works as metro construction progresses

Metro rail authorities have confirmed that civil construction work is actively progressing along the stretch between Porur and Poonamallee depot.

Express News Service

CHENNAI: CMRL has completed grade separator works between Mullaithottam and Karayanchavadi stations, marking a “crucial step” in the construction of the metro corridor.

As part of this development, a motor trolley was transported from Poonamallee depot to Mullaithottam station, reaching Pier No. 424 designated as the starting point for the grade separator construction. The road cum rail vehicle (RRV), essential for overhead equipment installations, was also moved from Poonamallee depot to Mullaithottam station.

Metro rail authorities have confirmed that civil construction work is actively progressing along the stretch between Porur and Poonamallee depot. The project remains on track, with plans to open the corridor for passenger services by late 2025, officials said.

Meanwhile, a total of 86,65 lakh passengers travelled in metro trains in the month of February.

Iran seeks 'greater' Indian role in West Asia peace push, flags rising Hormuz tensions

'Not an iota of truth': PM Modi rejects reports of tax on foreign travel

Israel, Lebanon say extending ceasefire despite new strikes

CBI arrests Pune chemistry lecturer alleged to be 'kingpin' in NEET UG paper leak

Sunetra Pawar tightens family grip on NCP, sidelines Praful Patel, Sunil Tatkare

SCROLL FOR NEXT