Fresh hurdles delay environmental clearance for Outer Ring Road project in Thiruvananthapuram

The environment ministry's expert panel has ordered a site inspection before clearance, bringing the project under renewed scrutiny.

Express News Service

THIRUVANANTHAPURAM: Despite the Kerala High Court’s intervention and the Centre’s recent assurance that compensation would be disbursed to around 6,500 families who surrendered their land for the long-pending Vizhinjam-Navaikulam Outer Ring Road (ORR) project, environmental clearance for the project remains pending.

The expert appraisal committee (EAC) under the ministry of environment, forest and climate change has mandated a site inspection before granting clearance, putting the project under renewed scrutiny.

A senior National Highways Authority of India (NHAI) official told TNIE that the Centre is yet to communicate the dates for the inspection, which is expected to take place in the coming days.

According to official sources, the EAC’s decision comes against the backdrop of recurring landslides across Kerala, including the recent tunnel-related accident in Wayanad. Concerns have also been raised over the proposed alignment between Thekkada and Navaikulam, where multiple tunnel sections are planned.

A petition filed by Aji R R, a resident of Vamanapuram, alleged that the proposed alignment passes through ecologically fragile hill ranges and the catchment area of the Vamanapuram river, posing risks of landslide and environmental degradation. The petitioner has sought a revision of the alignment.

Rejecting the allegations, Ajith G, president of the Vizhinjam ORR Land Owners Welfare Movement, claimed that vested interests were attempting to derail the project. “Around 6,500 families whose properties have been notified for acquisition have been waiting for compensation and project implementation for years.

The prolonged uncertainty has caused severe financial hardship to many families. Recently, a 36-year-old man from Irumpa died by suicide after facing financial distress allegedly linked to delays in the land acquisition process,” he said.

Responding to concerns over the tunnel stretches, an NHAI official said properly designed tunnels are often a more environmentally sustainable alternative to extensive hill cutting.

“We haven’t yet received any official communication regarding the proposed visit

by the expert appraisal committee. Once the visit is confirmed, our department and the other agencies concerned will jointly inspect the site,” the official said.

Concerns on alignment

  • EAC’s decision comes against the backdrop of recurring landslides across Kerala, including the recent tunnel-related accident in Wayanad, according to officials

  • Concerns have also been raised over the proposed alignment between Thekkada and Navaikulam, where multiple tunnel sections are planned

  • A petition alleges that the proposed alignment passes through ecologically fragile hill ranges and the catchment area of the Vamanapuram river, posing risks of landslide & environmental degradation

CJP, student protests: Govt softens on two demands, may not yield on Pradhan

'Do I need a character certificate?': Wangchuk hits back at critics

Indian national killed in Black Sea attack on commercial vessel; MEA condemns strike

PM Modi thanks people for 'insightful' responses to anti-paper leak video as Cabinet clears stricter law

India’s first hydrogen-powered train and why it matters

SCROLL FOR NEXT