Over 54,000 trees cut for Goa's upcoming Mopa international airport: CM Sawant

In a written reply tabled in the House, Chief Minister Pramod Sawant said that nearly 20 per cent work of the Mopa airport project has been completed till mid-December 2020.

PTI

PANAJI: A total of 54,176 trees have been cut for Goa's upcoming Mopa international airport, whose first phase is expected to be completed in 2022, state Chief Minister Pramod Sawant told the Legislative Assembly on Wednesday.

In a written reply tabled in the House, he said that nearly 20 per cent work of the Mopa airport project has been completed till mid-December 2020.

"Mopa airport's construction is in progress. The first phase is expected to be commissioned in 2022. The physical progress up to December 12, 2020, is 19.59 per cent," he said.

"A total of 54,176 trees were cut for the airport project, while 500 more trees were transplanted," he said.

This upcoming airport is a joint venture between GMR and the state government.

Jensen Huang built the company that powers AI. Now Nvidia must find a way forward without him

Sharad Pawar faces internal revolt over possible NCP merger with BJP-led NDA

Agri sector grew over 4% annually for first time since Independence; 50 cr people overcome poverty: PM Modi

Nvidia CEO Jensen Huang resigns amid affair, China spy allegations; CFO Colette Kress named interim chief

Owaisi backs Chandrashekhar Azad for UP chief minister's post, vows to stop BJP's third term