Emami Cement plant in Jajpur gets steady power

City-based AK Das Associates Ltd successfully completed the 220 KV line along with substation worked for the ECL project within the 10-month deadline.

From our online archive

BHUBANESWAR:  The Emami Cement Limited (ECL) at Kalinga Nagar Industrial area has been supplied uninterrupted power supply from the inter-state 400/220 KV New Duburi grid of Odisha Power Tranmission Corporation Ltd (OPTCL).Emami Cement Limited was allowed to receive 15 MVA power in 132 KV from OPTCL. However, taking its future expansion plan into consideration, ECL applied for 15 MVA power in 220 KV.

City-based AK Das Associates Ltd successfully completed the 220 KV line along with substation worked for the ECL project within the 10-month deadline. The cement company, which faced hurdles initially to avail the required power, got it after the intervention of OPTCL CMD Hemant Sharma.

Sharma had assured to construct an additional 220 KV switching station at the premises of ECL for the future use of OPTCL.Project Head of Kalinga Nagar unit, PK Singh said ECL will get uninterrupted 220 KV power supply due to successful energisation of the plant.

Delhi AQI data under scrutiny as monitoring stations go offline amid peak Diwali pollution

A year after Red Fort blast, empty homes, shattered dreams and scars that refuse to heal

'Jawans didn't buy PM's lies': Rahul repeats debate dare over Modi's 'Dimagi Naxal' jibe

Priyanka Gandhi likely to take centre stage in Congress' 2027 UP poll strategy

TN Deputy Speaker accused of assaulting man, forcing him to record video denying attack