The release from the ash pond flowing all over the village areas | Express 
Odisha

OPGC ash pond collapses, inundates villages

At around 8.15 am, the ash pond, measuring approximately 50 metre in length and 30 to 35 metre in depth, collapsed, sending ash water surging towards Sharadhapali.

Express News Service

JHARSUGUDA: In a troubling incident near Rengali, the Orissa Power Generation Corporation Ltd’s (OPGC) ash pond C in Ib Thermal Banharpali collapsed on Saturday morning leading to ash-laden water seeping into nearby Kantatikra and Saradhapalli villages in Kumharbandh Panchayat of Lakhanpur block in the district. 

At around 8.15 am, the ash pond, measuring approximately 50 metre in length and 30 to 35 metre in depth, collapsed, sending ash water surging towards Sharadhapali.

Without any other option, the villagers evacuated the area, and took refuge atop nearby ash pond A while authorities, including the police and district administration, immediately intervened to clear off the area.

Villagers in the affected areas are apprehensive of damage to crops and the fishermen too are left worried due to the potential threat to the Hirakud reservoir that could affect the region’s fisheries. The collapse has affected farmlands, impacting 32 families and 41 farmers. They have demanded compensation and relocation by the OPGC. Besides they cited a previous instance of water leak which they alleged was ignored by OPGC. The officials however, denied any such instance.

The affected ash pond (C), spanning 110 to 120 acre, collects ash from units 1, 2, and residual ash from units 3 and 4, reportedly accumulating 4,600 to 7,000 cubic metre daily. Meanwhile, local administrative authorities are investigating the cause of the embankment’s collapse. Tehsildar S Kumhar assured that damage assessment will be done and compensation disbursed accordingly.

During a visit to the site, MP Suresh Pujari expressed grave concerns about the possible consequences for villages and agricultural lands if the ash pond remains unchecked. “A swift resolution is the need of the hour and a scrutiny into alleged irregularities in the ash pond tendering process must be taken up,” he asserted . 

OPGC’s senior manager, HB Behera, confirmed a 20-foot crack in the ash pond, with ongoing repair work expected to take two to three days. The district collector is expected to visit the site on Sunday.

Maharashtra government scraps 5% Muslim quota in jobs, education; Opposition terms move ‘anti-minority’

Galgotias University asked to vacate AI Summit expo after Chinese robodog row

Those joining BJP became insignificant: Assam Congress chief on Bhupen Borah's plan to switch sides

SC asks Uttarakhand HC to decide plea of aviation firm against taking over of helipad by state

ECI sets March 16 date for biennial Rajya Sabha polls to 37 seats

SCROLL FOR NEXT