Talcher-Bimlagarh railway line cost soars to Rs 3,390 crore

ECoR is yet to get physical possession of balance 20 per cent of private land in Sundargarh district, while it is 90 per cent in Deogarh.

Prasanjeet Sarkar

ROURKELA: From Rs 727 crore, the cost of the ongoing Talcher-Bimlagarh new railway line project has officially escalated to a staggering Rs 3,390 crore primarily due to administrative failure in timely acquisition of land.

In a social media post on August 4, Rajya Sabha Member and former Union minister Dilip Ray said he raised the issue of the long-pending railway project in the Upper House of Parliament and sought a detailed statement on its progress, funding, land acquisition, and implementation status.

Ray said the government informed the Parliament that the 150-km Talcher-Bimalagarh railway line, sanctioned in 2003-04 at an estimated cost of Rs 727 crore, now has an updated project cost of Rs 3,390 crore. An expenditure of Rs 1,901 crore has already been incurred up to March 2026, while Rs 950 crore has been allocated for the new line during 2026-27.

He said the project has been moving steadily towards completion. Around 756 hectare out of the required 863 hectare of land has already been acquired. The 48-km Talcher-Khamar section has been commissioned, while construction is progressing on the remaining stretches with significant progress in land acquisition and construction of bridges. Forest and wildlife clearances have also been received for the Mahuldiha-Bimalagarh section.

The former Union minister said the Talcher-Bimalagarh railway line will be a transformative project for Angul, Deogarh and Sundargarh districts, enhancing connectivity, facilitating industrial and economic growth, and creating new opportunities for the people of western Odisha.

However, there was no mention of the project completion target which has been extended further. Under implementation for almost two decades, the progress of the project has been barely 32 per cent till now with the East Coast Railway (ECOR) quietly extending the completion target by another two years to March 2029.

Sources said the ECoR is yet to get physical possession of balance 20 per cent of private land in Sundargarh district, while it is 90 per cent in Deogarh. Tender for the remaining length of about 30 km from Mohuldiha (Sundargarh) to Barkote (Deogarh) is yet to be floated reportedly due to land hurdles in Deogarh.

No breakthrough in first talks; Jharkhand students continue JPSC protest

US Senate passes sanctions bill that may penalise countries buying Russian oil, gas and other exports

South Korea's stock market crash: Why AI wasn't the real story

Honour killing: 52-year-old arrested for drowning pregnant teen daughter in Agra’s Chambal river

CJP's Dipke urges PM Modi to focus on education, jobs in Independence Day address

SCROLL FOR NEXT