‘40 per cent works for modernising LBP canal over in Erode’

The chief engineer held a discussion with the farmers from the area, who requested him to construct a sidewall on the canal.

Express News Service

ERODE: As the date of releasing water draws closer, officials from water resources department (WRD) said that 40% works for the modernisation of LBP canal has been completed so far. C Sivalingam, Chief Engineer of WRD (Coimbatore Region), inspected the project works in Vaduganur in Erode on Saturday with other officials of the project.

An official from the WRD said, “The chief engineer held a discussion with the farmers from the area, who requested him to construct a sidewall on the canal. The project started on May 1, but due to non-cooperation from some farmers, the works couldn’t be carried out as planned. However, the works have been accelerated now and 40% of the works has been completed so far.”
"We plan to stop the works a week before the water will be released for 240 days on August 15. We plan to resume the work in May 2024 and complete it in August next year,” he added.

At least nine dead, several injured in massive Kolkata hotel fire

Income Tax Department flags 394 entities over suspicious foreign remittances, 36 professionals under scrutiny

UAE accuses Iran of firing ballistic missiles at shipping

Two moderate earthquakes hit Himachal Pradesh's Chamba, Kangra districts; no loss of life reported

Satyendar Jain, five others arrested in alleged Delhi Jal Board tender corruption case; AAP alleges BJP vendetta

SCROLL FOR NEXT