Speed up pre-monsoon maintenance work, min Thangam Thennarasu tells Tangedco officials

As part of the efforts, 31,328 damaged poles have been replaced, 29,943 leaning poles repaired, and 15,841 new poles added to the power network.

Express News Service

CHENNAI: Electricity Minister Thangam Thennarasu instructed chief engineers, during a review meeting at Tangedco’s headquarters on Wednesday, to speed up the ongoing pre-monsoon maintenance works. He noted that 88% of the work has been completed so far.

The maintenance activities, which began on July 1, are crucial to ensuring uninterrupted power supply. As part of the efforts, 31,328 damaged poles have been replaced, 29,943 leaning poles repaired, and 15,841 new poles added to the power network.

The minister also reviewed the implementation of announcements made during the Assembly sessions. Out of 108 announcements, 28, including the provision of 1.50 lakh free agricultural power connections and the conversion of overhead power lines to underground cables in temple towns like Srivilliputhur, Srirangam and Suchindram, have been fulfilled.

LIVE | West Asia war | Fake news to manipulate financial and oil markets: Iran parliament speaker on Trumps claims

Iran war: India among worst hit, GDP may drop 4% if conflict drags on, says Moody’s Analytics

What went wrong in speed boat accident where motorsport legend Hari Singh went missing?

'One nation one election' can be implemented from 2034, will save Rs 7 lakh crore: JPC chief Chaudhary

Why are gold and silver prices falling despite the West Asia war and global uncertainty?

SCROLL FOR NEXT