Madurai-Thoothukudi broad gauge line works under review as land acquisition progresses

Despite completion of a key stretch, insufficient funding and delays in land acquisition raise concerns over project timeline.

Jeyalakshmi Ramanujam

MADURAI: The works of the Madurai-Thoothukudi broad gauge (BG) line (via Arupukottai) and the Melmarudur-Tiruparankundram project are being kept under review, said Southern Railway assistant public information officer (PIO) J Kumarasubramanian in an RTI reply sought by one Dayanand Krishnan, seeking information regarding the BG line work.

In the RTI response, the PIO said that the Madurai-Thoothukudi new BG line via Arupukottai is 143.5 km in length. Of this, works on the Milavittan-Melmarudur, which is an 18 km stretch, was completed and authorised by the Commission of Railway Safety (CRS) on March 8, 2022. In the case of the remaining stretch from Melmarudur to Tiruparankundram (Madurai), land acquisition works are under way and the project is kept under review, the reply said.

Following the RTI reply, TNIE spoke to railway officials to clarify whether they received any communication to freeze the project. As of now, we have not received any communication from the Railway Board in this regard, and as usual, the department concerned is undertaking land acquisition works to implement the project, an official said on conditions of anonymity.

Speaking to TNIE, Dakshin Railway Employees Union Zonal Joint Secretary R Sankara Narayanan said that there was no possibility of freezing the project as the Milavittan-Melmarudur stretch has already been completed.

"After TNIE pointed out a delay in land acquisition on February 2, 2023, the Tamil Nadu Government passed a G.O. for land acquisition. At present, the Madurai Division of the Southern Railway has completed land acquisition. However, the central government has allotted only `100 crore for the project, and it is not enough to offer compensation for the land owners owing to the rise in the guideline value of land," he said.

Narayanan further stated that the railway needs to allot sufficient funds to complete the projects.

"There are no direct long route trains for the people of Arupukottai and Vilathikulam areas. If this project is implemented, they will benefit in all ways including freight movement. Currently, districts like Coimbatore and Krishnagiri export their products through Visakhapatnam or Bangalore. If the train route is implemented, it will automatically increase freight movement to Thoothukudi. All MPs should unanimously raise their voices to expedite the execution of these projects," he said.

When contacted, former Divisional Rail Users Consultative Committee (DRUCC) member R Pandiyaraja said that the railways had floated the tender for the Madurai-Thoothukudi BG line in 2016. Despite the passing of nearly eight years, the project is yet to attain completion.

"Allocation of `100 crore is not enough, as laying 1 km of line requires `15 crore. As per the RTI reply, the railways is yet to complete the remaining 125 km, and should pay compensation to the landowners for land acquisition. Hence, apart from the compensation, at least `1,875 crore should be allotted for completing the projects. We hope the railways complete the project before 2030," he said.

LIVE | West Asia conflict | War spreads to Lebanon as IDF strikes Hezbollah; Iran says 'will not negotiate'

Middle East conflict: Sensex crashes 3% at open, trims losses but still down by 1,000 points

PM Modi holds bilateral talks with Canadian PM Carney, reviews progress of strategic ties

Trump says US, Israel prepared to sustain Iran strikes for 'four to five weeks'

Blow after blow to the power of Iran and its proxy militias set stage for US-Israel attacks

SCROLL FOR NEXT