The rehabilitation plan has been drawn up taking into account concerns raised by the National Dam Safety Authority and other expert bodies over the safety of the barrages. Photo | Express
Telangana

Telangana: KLIS rehabilitation from mid-November, monsoon 2027 deadline

The designs will be placed before the Technical Oversight Committee under the Central Water Commission in New Delhi on October 5 for expert examination and recommendations.

Express News Service

HYDERABAD: The state government will begin comprehensive rehabilitation of the Medigadda, Annaram and Sundilla barrages, part of the Kaleshwaram Lift Irrigation Scheme, in mid-November and complete the works before the onset of the 2027 monsoon.

Speaking after chairing a review meeting with officials at his camp office here, Irrigation Minister N Uttam Kumar Reddy said the government had finalised the designs to restore the safety and operational reliability of all three barrages.

The rehabilitation plan has been drawn up taking into account concerns raised by the National Dam Safety Authority and other expert bodies over the safety of the barrages, Uttam said.

The plan prepared by the project designer includes strengthening the foundations through grouting, extending the stilling basins and constructing fresh cutoff walls. The measures are aimed at addressing deficiencies in the earlier energy-dissipation arrangements, foundation stability and under-seepage control.

“There will be no compromise on structural safety or the quality of rehabilitation. The works will be executed strictly on the basis of scientific studies and the recommendations of national technical institutions,” he said.

The designs are now being validated through computational fluid dynamics modelling at the Central Water and Power Research Station, Pune. The modelling will assess the hydraulic behaviour of the barrages and verify the effectiveness of the proposed energy-dissipation measures under different flow conditions.

The designs will be placed before the Technical Oversight Committee under the Central Water Commission in New Delhi on October 5 for expert examination and recommendations.

At the same time, Uttam directed Irrigation officials to complete all preparatory work so that there would be no delay once technical clearance is received. The Irrigation and Command Area Development Department is preparing detailed cost estimates and finalising the contractual mechanism required for government approval.

No halfway measures; focus will be on quality: Uttam

The paperwork will allow the department to immediately invite tenders and award the contracts once the designs are cleared, he said. The execution framework will include stringent quality-control procedures, independent testing and clearly defined timelines. Senior officials will monitor the progress continuously to ensure that the rehabilitation is completed before the next monsoon.

Uttam made it clear that the government would not opt for temporary measures and would instead focus on technically sound and durable rehabilitation of the three barrages.

“The three barrages will be operated only after the rehabilitation works are completed and the requisite safety clearances are received from the national authorities,” he said.

He directed the department to comply with the directions of the NDSA and ensure that every stage, from design validation and tendering to execution and final safety certification, is properly documented and subjected to expert scrutiny.

How a 1986 verdict is tied to the Vande Mataram case

For Tarique Rahman visit, Dhaka wants new water-share treaty

Lawyer turned granite mogul’s dark shadow

Arguments by serial practitioner of terrorism will not stand: EAM Jaishankar slams Pakistan at UNGA

'Unanimous approval': Election Commission denies internal rift over SIR, streamlines notice process